The Mumbai International Airport
Limited (MIAL) had proposed
diverting the river.
Consultants from the Indian
Institute of Technology, Bombay (IIT-B)
said that widening the culvert that
runs under the main runway is the
only option.
The report says diverting the Mithi
would not be possible because the
area is hilly.
“The culvert is 27 m wide and 4.1 m
high. The width should be increased
by 20 m,“ said the report, submitted
by IIT pro- fessor Kapil Gupta to
the Brihanmumbai Municipal
Corporation.
The BMC has been urging MIAL to
widen the culvert for the last two
years but because of several
security concerns, the airport
authority is yet to agree.
The
Mumbai International Airport
Limited's (MIAL) plan to divert the
flow of the Mithi River along
Andheri-Kurla road has been rejected
by an expert appoint- ed to study
the plan.
Professor Kapil Gupta, from the
Indian Institute of
TechnologyBombay was appointed by
the Brihanmumbai Municipal
Corporation (BMC) to study the plan.
Gupta has instead recommended the
widening of the culvert under the
runway, a suggestion the BMC had
also given.
“The culvert is 27 metres wide and
4.1 metres high. The width should be
increased by 20 metres to sustain
rainfall of 100 mm in an hour,“ says
the report submitted to the BMC on
March 15.
A
copy of the report is with Hindustan
Times.
The report says diverting the Mithi
along AndheriKurla road is not
possible because the area is hilly.
Civic sources said diversion will
require resettling more than 40,000
slum settlements.
“The report has said that widening
of the culvert is the only solution.
MIAL will have to undertake the
widening,“ said Additional Municipal
Commissioner, R.A. Rajeev.
The BMC has sent the report to the
government.
An
MIAL spokesperson said, “We have
submitted a report to the state
government, MMRDA and BMC addressing
the issues that will come up while
diverting the flow of the river. A
meeting will be held with the
chief minister in a month to decide
which plan is to be executed.“
If
the culvert under the run- way is
not widened and the Mithi overflows
in the monsoon, chances of water
logging on the runway are high.
The Chitale committee report of 2007
and the Central Water and Power
Research Survey had said the stretch
of the river near Krantinagar, Kurla,
should be widened to 100 metres
downstream and 40 metres upstream
and the culvert under the main
runway should be widened to 60
metres.
The BMC widened the river last year,
but until the culvert is widened
water logging will continue.
“The stretch of the river under the
runway is only 27 metres wide and
creates a bottleneck leading to
flooding.
When the Mithi swells, water enters
the runway affecting air traffic,“ a
civic official said requesting
anonymity.
The BMC has been pursuing the matter
with MIAL for two years. “The MIAL
had securi- ty concerns and was
worried the runway may collapse if
widening is undertaken,“ the civic
official said.